ProjectMallow General Hospital
-
LocationMallow, Co. Cork
-
ClientESS Modular
-
CompletionOctober 2023

Modular Ward Extension for Mallow General Hospital
Datum BCE completed a major project for ESS Modular at Mallow General Hospital in Co. Cork in October 2023. The project involved constructing a four-storey over basement, 48-bed modular ward extension. Positioned directly in front of the hospital’s main entrance and over the existing bus and set-down areas, the new building was seamlessly integrated into the existing hospital. Working within a live hospital environment and near critical services, Datum BCE developed site procedures and phasing plans to ensure uninterrupted medical care throughout the construction process.
Works included
- Site enabling works
- Concrete & formwork
- 250m long x 5m high concrete retaining wall
- 5 stairs
- 1 ramp
- MV grid connection
- Foul & storm drainage
- Watermain
- Oxygen lines
- Utilities
- Paths & kerbs
- Paving
- Tar
- Linemarking
- Remedial works